The first turbine unit of TPP in Soviet Gavan’ is synchronized with EES of Russia

The first turbine unit of the new TPP in Soviet Gavan’ a building of which is being completed by RusHydro in Khabarovsk krai is included into a network and synchronized with United power system of Russia. Within the complex tests, it was done a trail start of the turbine unit that has issued successfully the first kilowatt-hours into the power system.

Totally, on TPP in Soviet Gavan’ town, two modern turbine units of capacity per 63 MW each are mounted. The equipment of the turbine units is made with Russian enterprises: the steam turbines on Kaluga turbine plant, the generators on Novosibirsk enterprise “ELSIB”.

A building of TPP in Soviet Gavan’ is at a finishing stage. It is completed an erection of all three boiling units, steam turbines and generators, electric filters, transformers. There were installed under a voltage the objects of issue of station power: distributive plant, power transmission lines, transformer substations. At the finishing stage there are the finishing works as well as an erection of the equipment of fuel supply and auxiliary systems. Simultaneously, it is being continued a building of the objects of a circuit of issue of heat power and dwelling-house for service staff.

In the content of main equipment of the station, there are included three boiling units, two steam turbines and two electric generators. The station is equipped with an automatic control system of technological processes. The installed electric power of new TPP is of 126 MW, heat power – 200 Gcal/h, a design annual generation of electric power – 630 mln. kWhr.

The new power plant is intended for a replacement of leaving capacities of retired Mayskaya PP operating with high fuel flow, and it will become a source of power for further development of Soviet Gavan’ industrial and traffic hub, it will allow to cover the growing demands of the region in electric power. The station will provide a reliable heat supply and all the year hot water supply of industrial consumers and inhabitants in Soviet Gavan’. A liquidation of a number of low saving boiling houses in a result of starting of TPP will sufficiently improve an environmental situation on a territory of the town.

TPP in Soviet Gavan’ is one of four projects of investment program of RusHydro on a building of power objects in Far East that are being realized in accordance with an Order of President of RF. Three of them – the second phase of Blagoveshchensk TPP, the first phase of Yakutsk PP-2 and Sakhalin PP-2 – are already commissioned.